Dropped Wellhead Protection Structure During Decommissioning

When recovering a Subsea Xmas Tree, the load bearing capability of the wellhead connector was exceeded once the buoyancy effect of the seawater was removed.

The Wellhead Protection Structure (WHPS) sank to the seabed in an uncontrolled manner from the splash zone to land approximately 2m from the well centre. The WHPS was recovered at a later date.

To reduce the complexity of the recovery operations, a strategy to recover the WHPS, wellhead & tree as a single lift had been engineered. This required the WHPS to remain engaged onto the wellhead during the lift.

However, during the recovery the WHPS disengaged from the wellhead and sank back to the seabed. There was no other infrastructure remaining in the area. After following a management of change process lifting operations were resumed and the wellhead and xmas tree were recovered to the rig.

Later inspection of the WHPS (once recovered by vessel and returned to shore) led to the conclusion that the WHPS-to-wellhead connector had not been activated fully during its installation, prior to the well going on production.

Key Learning:

Equipment data gaps during decom planning are common but can often be bridged by additional engineering and risk assessment. If, however, the data gap cannot be resolved (in this case evidence of full activation of the WHPS-to-wellhead connector) a more conservative recovery plan should be used.

Download Alert

Rate this Alert

Your Rating

Average Rating

More from this Workgroup

Alert
Scis main logo colour

Potential Dropped Objects (PDOs) returned with units

In the offshore environment Potential Dropped Objects (PDO’s) are a major safety risk as the transportation of units is normally completed using cranes and lifting items great heights. This poses the risk of items falling and striking personnel in the vicinity. Over the years, many PDO’s have been d…

Alert
Scis main logo colour

Dropped Object Due to Corroded Deluge Flange

After landing a lower completion assembly on the drill floor and while retracting the deck crane whip line and twin hook stinger back through the v-door, the twin hook stinger swung to starboard causing one of the hooks to strike a blanking flange on the drill floor deluge line. The 4.95kg blanking …

Alert
Scis main logo colour

Rust Particle Enters Eye During Spool Removal

A Mechanical Tech was tasked with the removal of a spool. Due to the location of the spool, the technician had to work in a restricted space, lying on their back to access the flange bolts. During removal, the IP felt what they believed to be rust, hit their face. Following this, the IP re-positione…

Join over 185 organisations making a difference

Membership connects your organisation to shared expertise, practical resources and collaborative leadership in safety and wellbeing.

I Stock 2218565815